More information coming soon.
New Meter Request Process
Before the meter installation and activation process can commence, the following prerequisites must be completed by the Developer:
- Facility Capacity Fees (FCF)
- Certificate of Compliance
- Materials & Labor SOW (funding)
- Project Tract Map recorded with L.A. County
- Project is installed, tested, and active
- Project Punchlist is complete
- Close-Out Documents
As-Built & Record Drawings
As-Built Survey Data
Final Geotechnical/Compaction Report
Easements (if applicable)
Download New Meter Request Process
Email newmeterrequest@scvwa.org for assistance.
Meter Installation Process
Meter Activation Process
Construction Meter Requests
There are retail costs that may be due when requesting a construction water meter.
- To request a flanged construction meter (size 4" and 6"), please complete the Flanged Construction Meter Application and submit it by email to constructionmeterflanged@scvwa.org.
- To request a temporary hydrant meter (size 2" and 2 1/2"), please contact Customer Care at ccare@scvwa.org or 661-294-0828.
NOTE: While Los Angeles County Water Works District #36 (LAWWD#36), which services the Val Verde and parts of the Castaic area, was not part of the merger, SCV Water will continue to supply imported water to LAWWD#36. New water connections and/or upsizing a meter within LAWWD#36 service area are still subject to SCV Water’s Regional Facility Capacity Fees/Charges. If your new water connection is within LAWWD#36 service area you will need to contact them directly regarding their water connection/meter costs and fees.